Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Installation of the first 26 km submarine interconnection cable between Fardioua (Morocco) and Tarifa (Spain) was completed and the link entered operation in August 1997, providing an initial exchange capacity of 700 MW for the REMO project.