Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Jan De Nul Group completed the offshore export cable installation for the Race Bank transmission system, installing two approximately 71 km, 220 kV HVAC export cables between the wind farm and the mainland and an additional ~6 km interconnector cable between the two offshore substations. Using the cable-laying vessel Isaac Newton and bespoke low-ground-pressure trenching machines Sunfish and Moonfish to cross The Wash nature reserve, the company installed and buried roughly 148 km of export and interlink cables that now form part of the Race Bank OFTO transmission assets, meeting stringent environmental and technical requirements.