Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
For the Podgora–Hvar 35 kV submarine cable project, HEP ODS’s regional unit Elektrodalmacija Split procured KRKA SUB MARIS d.o.o. of Split as a subcontractor to work alongside its own staff in executing the technically demanding subsea cable laying operations between Čaklje and Bogomolje.