Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
Hrvatska elektroprivreda’s distribution operator (HEP ODS) invested around HRK 17 million in the 12 km, 35 kV Podgora–Pogorila submarine cable linking the Croatian mainland (Podgora/Čaklje) with the eastern part of Hvar island, as part of a broader 2020 programme to improve power supply on Hvar. The same article notes a further planned investment of about HRK 15 million for the future Bogomolje substation that this cable will supply.