Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Around early July 2024, 50Hertz completed a four‑week trial operation of the third and final 220 kV AC cable system for the Ostwind 2 offshore grid connection off the coast of Rügen. This trial operation tested the last of three export cable systems linking the Arcadis Ost 1 and Baltic Eagle offshore wind farms to the onshore grid at Lubmin, enabling the Ostwind 2 connection to move into continuous operation nearly three months earlier than planned and ultimately integrate up to 750 MW into the 50Hertz high‑voltage network.