Ostwind 2 grid connection system commissioned and operational.
Around early July 2024, 50Hertz completed a four‑week trial operation of the third and final 220 kV AC cable system for the Ostwind 2 offshore grid connection off the coast of Rügen. This trial operation tested the last of three export cable systems linking the Arcadis Ost 1 and Baltic Eagle offshore wind farms to the onshore grid at Lubmin, enabling the Ostwind 2 connection to move into continuous operation nearly three months earlier than planned and ultimately integrate up to 750 MW into the 50Hertz high‑voltage network.
Third Ostwind 2 cable system (OST-2-3, connecting Baltic Eagle) installation commenced 2022. Commissioned April 2024 after trial operation completing July 2024.
By December 2021, the second of the three 220 kV export cable systems for the Ostwind 2 offshore grid connection in the German Baltic Sea had been successfully laid on the seabed, bringing the grid connection of Iberdrola’s Baltic Eagle wind farm another step closer and fulfilling 50Hertz’s commitment to install two cable systems within five years.
By September 2021, 50Hertz had completed the laying of the first of three Ostwind 2 sea/export cable systems, establishing the grid connection from the offshore route to the Arcadis Ost 1 wind farm as part of the 220 kV AC grid connection to Lubmin.
First Ostwind 2 cable section laid by March 2021 by Boskalis/NKT consortium. First cable system completed September 2021. Contract awarded November 2018.
NKT began cable production at Karlskrona (Sweden) and Cologne (Germany) at beginning of 2020 for approximately 200 km of 220 kV three-core submarine export cables.
Royal Boskalis Westminster, contracted by 50Hertz for the Ostwind 2 offshore grid connection, planned to commence unexploded ordnance (UXO) survey activities in 2019 as part of a wider export cable installation project that will link the Arcadis Ost 1 and Baltic Eagle wind farms to the Lubmin onshore substation.
As part of Boskalis and NKT’s export cable contract for Ostwind 2, geophysical seabed and water-depth surveys were scheduled to start in 2019 to support route engineering and installation of approximately 270 km of 220 kV export cables between the Arcadis Ost 1 and Baltic Eagle offshore wind farms and the Lubmin substation.
50Hertz awarded NKT a contract to supply the Ostwind 2 export cable system, under which NKT will provide approximately 270 km of 220 kV high‑voltage AC XLPE offshore export cable and 8 km of 220 kV AC XLPE onshore cable to connect the planned Arcadis Ost 1 and Baltic Eagle wind farms to the onshore substation in Lubmin, Germany; the order, valued at around EUR 300 million, is NKT’s largest ever AC high‑voltage export cable order and involves manufacturing at its Karlskrona (Sweden) and Cologne (Germany) plants with production scheduled to start in 2020.