By December 2021, the second of the three 220 kV export cable systems for the Ostwind 2 offshore grid connection in the German Baltic Sea had been successfully laid on the seabed, bringing the grid connection of Iberdrola’s Baltic Eagle wind farm another step closer and fulfilling 50Hertz’s commitment to install two cable systems within five years.