Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
On 10 July 2015, the Ministry for Energy of Mecklenburg-Western Pomerania granted 50Hertz approval for the Ostwind 1 sea cable route within German territorial waters (12‑nautical‑mile zone), providing the second of three permits needed for the export cable route.