Ostwind 1 grid connection system commissioned and operational.
50Hertz commenced offshore preliminary works for Ostwind 1 in August 2015 following BSH offshore route approval on 10 July 2015. Cable pre-lay run planned end of 2015.
50Hertz held construction start ceremony for Ostwind 1 grid connection on 27 August 2015. Planning approval for onshore route granted 9 March 2015.
Authority: Bundesamt für Seeschifffahrt und Hydrographie · Licence: Planning approval decision/permit for the Ostwind 1 sea cable route in the Exclusive Economic Zone (EEZ)
The Federal Maritime and Hydrographic Agency (BSH) issued a planning approval decision on 13 August 2015 for the Ostwind 1 sea cable route within the German Exclusive Economic Zone (EEZ), approving the last 20‑kilometre section so that the entire export cable route for connecting the Wikinger and Arkona wind farms to Lubmin was fully permitted.
Authority: Ministry for Energy of Mecklenburg-Western Pomerania · Licence: Approval/permit for the Ostwind 1 sea cable route in territorial waters (12‑nautical‑mile zone)
On 10 July 2015, the Ministry for Energy of Mecklenburg-Western Pomerania granted 50Hertz approval for the Ostwind 1 sea cable route within German territorial waters (12‑nautical‑mile zone), providing the second of three permits needed for the export cable route.
Authority: Ministry for Energy of Mecklenburg-Western Pomerania · Licence: Approval/permit for the Ostwind 1 land cable route
The Ministry for Energy of Mecklenburg-Western Pomerania granted 50Hertz approval for the land route of the Ostwind 1 offshore grid connection on 9 March 2015, issuing one of three permits required for the export cable route between the Westlich Adlergrund wind farm cluster and the Lubmin substation.