Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 25 April 2011, Vattenfall completed three months of export cable engineering works for the Ormonde offshore wind farm, finishing the installation and burial of the 42 km, 132 kV export cable in a single uninterrupted operation from the shore to the offshore substation. The completed export cable and associated connection works between the offshore substation and the Heysham onshore substation established the physical link to the National Grid, representing a key milestone for the Ormonde offshore transmission assets later operated by TC Ormonde OFTO.