Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
In 1985 a 380 kV submarine power cable with a transmission capacity of about 1000 MVA was laid through the Strait of Messina between mainland Italy and Sicily, replacing the overhead line carried by the Pylons of Messina and enabling the first power transmission on the new subsea interconnector.