Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Offshore construction start projected for 2030 using the COD-minus-2-years heuristic anchored to the LanWin3 (NOR-11-1, 50Hertz) grid system IBN 2032 per BSH FEP 2025 amendment Tabelle 7. Offshore wind-farm construction typically begins ~2 years before COD. Subject to FID, supplier selection, vessel availability and supply-chain status. Date precision is year-level given the planning-stage maturity.