Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
From January 2017, the Nobelwind offshore wind farm on Bligh Bank began producing its first energy, exporting via a 220 kV interconnector cable from the Nobelwind OHVS to the Northwind OHVS and then through the existing 220 kV Cableco export cable from Northwind to shore at Zeebrugge. This initial energisation represented the first power from Nobelwind transmitted over the Northwind–Nobelwind shared export connection into the Elia grid.