Northern Aegean Interconnection Phase B : Skyros - Euboea
22 January 2025
Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 22 January 2025, ADMIE announced that the final phase of the international tender for a framework agreement to lay down subsea cables for the electrical interconnections of the Dodecanese and Northeastern Aegean islands had started, with Fulgor, Nexans Norway and Prysmian Powerlink invited to submit binding financial and technical offers. This framework covers the 150 kV AC submarine cable packages for all included island links, among them the Skyros–Euboea connection within the Northeastern Aegean interconnection.