Northern Aegean Interconnection Phase B : Skyros - Euboea
October 2024
Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In October 2024, the second phase of IPTO/ADMIE’s tender process for the submarine cable projects of the Dodecanese and North‑East Aegean interconnections commenced, initiating the stage in which prequalified companies would be invited to submit final financial and technical offers. The framework, with an initial budget of EUR 1.7 billion and a six‑year duration, includes the cables serving the Northeastern Aegean scheme that connects islands such as Skyros to Evia.