Northern Aegean Interconnection Phase B : Skyros - Euboea
Date TBD
Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
Independent Power Transmission Operator (IPTO) reports that the seabed survey for the Skyros–Evia route, part of the Northeast Aegean islands electrical interconnections linking Skyros to the Aliveri substation on Euboea, has been completed following the award of study and marine survey contracts for the region in November 2023. This completed seabed investigation is a key early-development milestone for the Northern Aegean Interconnection Phase B: Skyros–Euboea, supporting route design and project maturity within IPTO’s wider island interconnection investment program.