Voice of Renewables reports, citing Litgrid, that due to ongoing reconstruction works at the Kruonis 330 kV transformer substation and reduced availability of balancing capacity, NordBalt’s transmission capacity will be limited between 20 and 30 October 2025 to 438 MW for imports and 356 MW for exports.