Voice of Renewables reports, citing Litgrid, that due to ongoing reconstruction works at the Kruonis 330 kV transformer substation and reduced availability of balancing capacity, NordBalt’s transmission capacity will be limited between 20 and 30 October 2025 to 438 MW for imports and 356 MW for exports.
By 10 October 2025, Litgrid had completed annual planned maintenance on the NordBalt converter station in Klaipėda, carrying out preventive maintenance and fault repairs on the converter, control system, cooling system and outdoor switchyard during a scheduled outage in line with manufacturer instructions and transmission network regulations.
Following completion of scheduled maintenance in Lithuania, the NordBalt electricity interconnection was re‑energised and made available for day‑ahead trading on Friday 10 October 2025 at 14:27, restoring normal operation two days earlier than initially planned.
On 11 December 2020, cable manufacturer NKT and Lithuanian TSO Litgrid entered into a three‑year service agreement covering part of the NordBalt interconnector, ensuring fast vessel mobilization, skilled jointer support and a tailored preparedness plan to quickly restore the Sweden–Lithuania HVDC link in case of cable damage, thereby strengthening security of supply for Lithuania and complementing an existing service agreement with Swedish TSO Svenska kraftnät for the onshore Swedish section.
In the early hours of Wednesday 2 December 2020, the NordBalt power interconnection between Lithuania and Sweden went offline due to a failure at the Nybro converter station in Sweden, with teams from Svenska Kraftnät and Hitachi ABB Power Grids mobilised to identify and rectify the fault.
By August 2020, AP Sensing’s distributed temperature sensing (DTS) fiber‑optic monitoring system had been selected and installed to monitor parts of the 450 km, 700 MW NordBalt subsea power link between Sweden and Lithuania, with three DTS units deployed at Klaipeda and Nybro converter stations and at Arby in Sweden to provide continuous condition monitoring of the subsea and onshore cables.
In June 2020, the NordBalt high‑voltage direct current interconnection experienced a malfunction for the first time since 2018, when a failure occurred in an underground cable joint approximately 30 km from the Nybro substation on the Swedish side, temporarily disrupting the link.
On the evening of Thursday 11 May 2017, the Lithuania–Sweden NordBalt interconnection went offline for about 15 hours due to a logical error in the IT-based control system at the Nybro station in Sweden, temporarily interrupting power flows and requiring activation of Lithuania’s Kruonis pumped storage plant as emergency reserve.
The NordBalt HVDC Light subsea interconnection was handed over by Hitachi Energy to the transmission system operators Svenska kraftnät (Sweden) and Litgrid (Lithuania) in June 2016, marking contractual completion of the turnkey project including the converter stations and submarine and land cable system.
The 450 km, 700 MW NordBalt subsea power link between Lithuania and Sweden, developed by Litgrid and Svenska Kraftnät, was launched in February 2016, marking the start of commercial operation of the interconnector.
| Sweden | LT | |
|---|---|---|
| Landfall | Nybro, Sweden | Klaipėda, LT |
| Grid Connection | 400 kV Nybro substation | 330 kV Klaipėda substation |
Sweden
LT