On 2 February 2016, the NordBalt HVDC interconnection between Sweden and Lithuania began trial operations, initiating power transmission at around 30 MW with a plan to ramp up over two weeks, after tests originally scheduled for December had been postponed due to a fire near the Swedish substation.