Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
According to DEDDIE’s network development appendices, the medium-voltage submarine interconnection between Nisyros and Tilos consists of two 20 kV cables (3 x 35 mm² Cu), each 16,000 m long for a total of 32,000 m, listed with a construction year of 1989, indicating that installation of all planned interconnector cables was completed in 1989.