Equinor’s partial electrification project for the Halten area platforms secured a 135 MW capacity reservation in the Norwegian power grid from system operator Statnett, covering the planned grid connection and power cable from shore (via Tømmervika/Abelvær) to the Equinor-operated Heidrun, Åsgard B and Kristin platforms. This capacity reservation indicated that grid access was allocated for the Halten area power-from-shore solution before the project was later discontinued for profitability reasons.