In early 2026, TenneT commenced field and soil investigations for Net op zee Nederwiek 3, including ground investigations around the Haringvlietdam and in Geertruidenberg, to characterise onshore subsurface conditions along the export cable route and at the future converter station location serving the Nederwiek III wind farm. [Mirrored from sibling Nederwiek III wind-farm record (69f4bf99e60465b367d612fb) during the 19 May 2026 grid/wind event-attribution cleanup. This event describes grid-scope activity (Net op zee Nederwiek 3 / LionLink) that was originally attributed to the wind farm by the offshore_wind_enricher and has now been corrected onto the Nederwiek 3 grid record.]
In July 2025, TenneT initiated drone-based investigations for unexploded ordnance (UXO) along the planned cable route for Net op zee Nederwiek 3, which will connect the Nederwiek III wind area to shore, as reported in a project news item titled "Drone onderzoek naar onontplofte explosieven langs kabelroute Nederwiek 3". [Mirrored from sibling Nederwiek III wind-farm record (69f4bf99e60465b367d612fb) during the 19 May 2026 grid/wind event-attribution cleanup. This event describes grid-scope activity (Net op zee Nederwiek 3 / LionLink) that was originally attributed to the wind farm by the offshore_wind_enricher and has now been corrected onto the Nederwiek 3 grid record.]
Upgrade to access detailed cable specifications, supply chain data, projected timeline, financial analysis, and more.
Net op zee Nederwiek 3 (Nederwiek 3) is a TenneT-led offshore grid connection designed to transport electricity from the Nederwiek wind energy zone to the Dutch onshore high-voltage network. The connection is specified as a 2 GW (2,000 MW) ±525 kV HVDC Grid Connection System (GCS) consisting of a...
Owners
Net op zee Nederwiek 3, Nederwiek 3 offshore grid, GCS Nederwiek 3, GCS Nederwiek III
At the beginning of 2025, Dutch Climate and Green Growth Minister Sophie Hermans included the LionLink hybrid interconnector, which will use the Nederwiek 3 offshore grid connection as its Dutch offshore hub, in the Netherlands’ latest Offshore Wind Energy Development Framework. This policy decision by the Ministry of Climate and Green Growth formally embeds LionLink within the national offshore wind and grid development framework and enables TenneT to proceed with investments related to the project and its integration with Nederwiek 3.
On 30 January 2025, the Ministers of Climate and Green Growth (KGG) and of Housing and Spatial Planning (VRO) adopted a voorbereidingsbesluit for Net op zee Nederwiek 3, entering into force the same day, to prevent spatial developments that could obstruct implementation of the offshore grid connection. [Mirrored from sibling Nederwiek III wind-farm record (69f4bf99e60465b367d612fb) during the 19 May 2026 grid/wind event-attribution cleanup. This event describes grid-scope activity (Net op zee Nederwiek 3 / LionLink) that was originally attributed to the wind farm by the offshore_wind_enricher and has now been corrected onto the Nederwiek 3 grid record.]
Phase 1 of the environmental impact report (Milieueffectrapport, MER fase 1) and the Integral Effect Analysis (IEA) for Net op zee Nederwiek 3, covering cable route and converter station alternatives near Geertruidenberg and Moerdijk, were completed and formally made available to support ministerial selection of a preferred alternative. [Mirrored from sibling Nederwiek III wind-farm record (69f4bf99e60465b367d612fb) during the 19 May 2026 grid/wind event-attribution cleanup. This event describes grid-scope activity (Net op zee Nederwiek 3 / LionLink) that was originally attributed to the wind farm by the offshore_wind_enricher and has now been corrected onto the Nederwiek 3 grid record.]
In June 2023, Belgian survey company GEOxyz began work on the Nederwiek 3 (NW3) export cable route under a contract from TenneT covering both geophysical and geotechnical route surveys from Stellendam to Geertruidenberg, with optional offshore and nearshore sections near the wind farm. GEOxyz had mobilised dedicated survey vessels Geosurveyor VIII and Geosurveyor V for the inland and nearshore parts of the route, with other assets scheduled for offshore, ultra‑shallow and land sections. The geotechnical scope includes seabed investigations with a required penetration depth of around 10 m for geotechnical sampling, using a novel marine sampling technique to obtain high‑quality soil samples. Data from these surveys will be used to build a geological model of the cable corridor and feed into a Burial Assessment Study to inform cable design and installation methodology. [Mirrored from sibling Nederwiek III wind-farm record (69f4bf99e60465b367d612fb) during the 19 May 2026 grid/wind event-attribution cleanup. This event describes grid-scope activity (Net op zee Nederwiek 3 / LionLink) that was originally attributed to the wind farm by the offshore_wind_enricher and has now been corrected onto the Nederwiek 3 grid record.]
From 2 June to 13 July 2023, the Ministry of Climate and Green Growth (KGG), via Bureau Energieprojecten (RVO), ran a public consultation on the draft Notitie Reikwijdte en Detailniveau (concept-NRD) for the environmental impact assessment (MER) of Net op zee Nederwiek 3, the 2 GW offshore grid connection for the Nederwiek wind energy area. [Mirrored from sibling Nederwiek III wind-farm record (69f4bf99e60465b367d612fb) during the 19 May 2026 grid/wind event-attribution cleanup. This event describes grid-scope activity (Net op zee Nederwiek 3 / LionLink) that was originally attributed to the wind farm by the offshore_wind_enricher and has now been corrected onto the Nederwiek 3 grid record.]
TenneT selected Belgian survey company GEOxyz to carry out geophysical and geotechnical route surveys for the export cable corridor of the Nederwiek 3 offshore grid connection between the Nederwiek offshore wind farm zone in the North Sea and the Dutch onshore grid at Geertruidenberg or Moerdijk. By June 2023, GEOxyz had mobilised its survey vessels Geosurveyor VIII and Geosurveyor V for inland and nearshore sections from Stellendam to Geertruidenberg, with Geo Ocean III or Geo Ocean VI scheduled for offshore work, supported by Geodrone ASV and aerial UAV teams for ultra‑shallow waters and land sections. The surveys are intended to map seabed and lakebed topography, identify obstructions, and provide data for a geological model and Burial Assessment Study to define export cable design and installation parameters for the Nederwiek 3 connection.
On 23 June 2023, TenneT awarded Belgian survey specialist GEOxyz a contract to perform combined geophysical and geotechnical surveys for the export cable route of the Nederwiek 3 Offshore Wind Farm in the Netherlands. Under the contract, GEOxyz will execute the route survey for the inland section in lake and riverine environments between Stellendam and Geertruidenberg, with optional scope covering the offshore section near the Nederwiek wind farm and the nearshore area south of the Port of Rotterdam. The work aims to investigate the suitability of the envisaged cable corridor, map seabed topography, and identify obstructions so that a geological model and Burial Assessment Study can be produced to inform cable design and installation methodology. [Mirrored from sibling Nederwiek III wind-farm record (69f4bf99e60465b367d612fb) during the 19 May 2026 grid/wind event-attribution cleanup. This event describes grid-scope activity (Net op zee Nederwiek 3 / LionLink) that was originally attributed to the wind farm by the offshore_wind_enricher and has now been corrected onto the Nederwiek 3 grid record.]
TenneT selected Belgian company GEOxyz to carry out geophysical and geotechnical surveys for the export cable route for the Nederwiek 3 offshore grid connection between the Nederwiek offshore wind farm area in the North Sea and an onshore landing point at Geertruidenberg or Moerdijk. The contract covers inland lake and riverine sections from Stellendam to Geertruidenberg and optionally the offshore and nearshore sections south of the Port of Rotterdam, with GEOxyz deploying a specialised fleet and delivering a geological model and Burial Assessment Study to inform cable design and installation.
Under a contract from TenneT for the Nederwiek 3 offshore grid connection, GEOxyz began geotechnical investigations along the planned underground high‑voltage export cable route linking the Nederwiek offshore wind farm area to Geertruidenberg or Moerdijk. The campaign, for which GEOxyz has mobilised dedicated survey vessels for inland and nearshore sections and scheduled offshore vessels, includes geotechnical sampling to a penetration depth of 10 metres using a novel marine technique to obtain high‑quality soil data. These data will feed into a geological ground model and a Burial Assessment Study that will define key technical parameters for the 2 GW HVDC export cable design and installation methodology and help minimise risks from challenging ground conditions and potential unexploded ordnance along the route.
TenneT awarded NKT a supply and installation contract for 525 kV HVDC cable systems covering several of its 2 GW offshore grid connection projects, including the Nederwiek 3 connection in the Netherlands. Under this multi-year agreement, NKT will realise the export cable systems for Nederwiek 3, as well as Doordewind 1 and Doordewind 2, as part of TenneT’s wider 2 GW programme to deliver multiple high-capacity offshore grid links by 2031.
In the Netherlands Enterprise Agency’s 2025 Offshore Wind Energy workshop materials, TenneT lists Nederwiek 3, with its land station at Geertruidenberg, among the projects under the heading "Hitachi Energy / Larsen & Toubro supporting 2 GW Programme". This indicates that Hitachi Energy and Larsen & Toubro are the contracted consortium supporting delivery of the 2 GW offshore grid connection systems for a group of TenneT projects that includes Nederwiek 3.
In 2022, the Dutch government decided to start the spatial planning procedure for the Net op zee Nederwiek 3 connection, examining options to bring power from the Nederwiek wind energy area ashore via the Geertruidenberg or Moerdijk region. This decision launched the formal spatial and permitting process for the offshore grid connection that will serve the Nederwiek 3 offshore wind farm. [Mirrored from sibling Nederwiek III wind-farm record (69f4bf99e60465b367d612fb) during the 19 May 2026 grid/wind event-attribution cleanup. This event describes grid-scope activity (Net op zee Nederwiek 3 / LionLink) that was originally attributed to the wind farm by the offshore_wind_enricher and has now been corrected onto the Nederwiek 3 grid record.]
Through the 2021 "Verkenning aanlanding wind op zee 2030" (VAWOZ 2030) system study, reported to Parliament on 2 December 2021, the Dutch government assessed options for landing additional offshore wind and concluded that a 2 GW connection from wind energy area Nederwiek Noord to Geertruidenberg or Moerdijk is promising, providing the system basis for the Net op zee Nederwiek 3 grid connection serving the future Nederwiek III wind farm. [Mirrored from sibling Nederwiek III wind-farm record (69f4bf99e60465b367d612fb) during the 19 May 2026 grid/wind event-attribution cleanup. This event describes grid-scope activity (Net op zee Nederwiek 3 / LionLink) that was originally attributed to the wind farm by the offshore_wind_enricher and has now been corrected onto the Nederwiek 3 grid record.]