Under the framework agreement signed 20 April 2023, GE Vernova Grid Solutions was selected by TenneT for EPCI of the 2 GW, 525 kV HVDC converter stations for Nederwiek 2 at Maasvlakte. Call-off confirmed June 2024. Steel cutting for Nederwiek 2 platform commenced February 2026 at Seatrium's Tuas yard.