Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Onshore construction for TenneT's Net op zee Nederwiek 2 connection at Maasvlakte, including installation of underground land cables from Slufterstrand to the converter station area and related civil works on the beach, is reported as underway by 16 February 2026. Windtech International describes this work as progressing and notes that the land cable phase has been completed, indicating that onshore construction started no later than this date (later than the originally projected June 2024 start).