Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Projected cable installation start for Nederwiek 2 at 2028-01-01 (approximate). The projections agent on 2026-04-13 initially confirmed this event at 2026-06-01, but its own Phase 1 log then acknowledged this was a mistake: no specific evidence of actual cable installation for Nederwiek 2 has yet been reported. TenneT's 2023 framework announcement mentioned generic onshore cable laying from 2025 and offshore from 2026, but those are portfolio-level timelines not Nederwiek 2 specifics. Given the revised Q2 2032 COD (reNews 2024) and the 2GW programme sequence (IJmuiden Ver Beta commissioning 2029, other links in subsequent years), export cable installation for Nederwiek 2 is realistically around 2028. Reverted to projected and delayed to 2028-01-01 during manual audit review because the projections agent could not use delay_event on a confirmed event in the same session.