Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
For Phase 2 of the Net op zee Nederwiek 1 grid connection project, the draft Water Permit (Watervergunning) was available for public inspection from 15 December 2023 to 25 January 2024. An appeal was subsequently lodged with the Administrative Jurisdiction Division of the Council of State against the definitive decisions, but this appeal was later withdrawn, making the water-related decisions irrevocable and bringing the permit into legal force.