TenneT has set a milestone date of 31 March 2031 for the delivery of the 2 GW HVDC grid connection system for Nederwiek I-A (the Nederwiek 1 offshore grid connection), meaning the HVDC connection is planned to be fully handed over and available to transmit power from the offshore wind farms to the onshore grid at Borssele/Sloegebied. This milestone is defined within the 2 GW standard framework for the Grid Connection System Nederwiek I-A, which comprises the offshore platform and export cables built and operated by TenneT.