Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Windpowernl, citing TenneT, reports that onshore cables for the IJmuiden Ver Alpha and Nederwiek 1 grid connections arrived in Vlissingen with construction consortium NRG scheduled to begin installing the underground land cables from February 2026 along the route from De Piet harbour in Arnemuiden to the converter stations in the Sloe industrial zone. This marks the start of onshore cable installation for Nederwiek 1 around February 2026, later than the original January 2025 projection.