Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
Site N-9.5 designated in the BSH Flächenentwicklungsplan 2025 amendment (30 January 2026) as a North Sea cluster-9 site paired with NOR-9-4 (BalWin5) for grid connection. 2028 auction year scheduled; commissioning targeted ~2033 Q3 per FEP Tabelle 7.