Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Offshore construction start projected for 2032 using the COD-minus-2-years heuristic anchored to the BorWin7 (NOR-6-4, Amprion) grid system IBN 2034 Q3 per BSH FEP 2025 amendment Tabelle 14. Subject to future BNetzA auction, FID, supplier selection and supply-chain status. Date precision is year-level given the long lead time.