Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Offshore construction start projected for 2030 using the COD-minus-2-years heuristic anchored to the LanWin5 (NOR-13-1, TenneT) grid system IBN 30 Sep 2032 per TenneT §17d EnWG completion-date filing (post-ASG-Nordsee bypass). Subject to 2027 auction outcome, subsequent FID, supplier selection and supply-chain status. Date precision is year-level given the planning-stage maturity.