N-13.1 scheduled for the 2027 BNetzA auction round per BSH FEP 2025 amendment (30 January 2026, Tabelle 7). The site was originally in the 2026 auction round but was shifted to 2027 by Cabinet decision 28 January 2026 alongside five other sites. Site is paired with NordSee Energies 2 (TotalEnergies, N-11.2, already awarded June 2024) on the LanWin4 (NOR-11-2) 2 GW HVDC grid connection. No developer yet awarded.