Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
Following assessment of comments from the participation procedures, BSH completed the suitability assessment for sites N-10.1 and N-10.2 and determined their suitability for the construction and operation of offshore wind farms by legal ordinance, implemented through the 5th Ordinance on the Implementation of the Offshore Wind Energy Act (5th WindSeeV) issued and published on 28 January 2025, which is a prerequisite for the Federal Network Agency to tender the N-10.1 area.