N-10.1 (fixed-bottom ~2 GW, retender 2027+)
30 September 2032
Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
BSH ‘Änderung des Flächenentwicklungsplans (FEP) 2025’ dated 30 Jan 2026 (Table 6) states for offshore wind site N-10.1: auction year 2027 and ‘Inbetriebnahme der auf den Flächen jeweils bezuschlagten WEA’ in ‘2032 (QIII)’. Interpreting the regulator-stated inbetriebnahme quarter as the wind farm’s planned full entry into service for the site’s awarded project(s).