Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In August 2017, Elia awarded offshore services provider DEME the Modular Offshore Grid (MOG) submarine power cable project, covering installation of approximately 85 km of subsea export cable using the vessel Living Stone to connect the Offshore Switch Yard platform to the Stevin onshore station at Zeebrugge and to the Rentel offshore substation in the Belgian North Sea.