NVE issued its recommendation (innstilling) to OED on 30 September 2013 for the 300 (420) kV Modalen-Mongstad transmission line. NVE recommended an overhead line from Steinsland (Modalen) via Haugsvaerdalen and Froyset to Iledalsvagen, a submarine cable crossing of Fensfjorden to Mongstad, then overhead line to Lindas transformer station. The total route was approximately 62.2 km comprising 55.2 km overhead line and 7 km submarine cable.