Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
BKK Nett submitted a consent application to NVE in September 2010 for the 300 (420) kV Modalen-Mongstad transmission line, including a submarine cable crossing of Fensfjorden. The application covered approximately 62 km of new transmission line from Modalen to Mongstad, of which around 7 km would be submarine cable across the fjord. Two supplementary applications with revised route alternatives followed in May 2012 and December 2012.