Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Nexans was selected and contracted to supply approximately 80 kilometres of low- and medium-voltage cable, including the submarine cable, for the electricity network project on Torsö, which includes the sea cable interconnection between Mariestad and Torsö and 55 new transformer stations. The company, based in Grimsås in Tranemo municipality, received the order and subsequently delivered the equipment, with each drum carrying about 1,300 metres of submarine cable weighing just over 13 tonnes.