Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
For the Lillgrund offshore grid connection, the offshore substation was awarded to a team in which ISC A/S in Copenhagen was responsible for the substation’s structural design, Bladt Industries constructed the substation structure, and Siemens acted as subcontractor for the electrical part of the substation. The resulting cylindrical offshore substation houses the main 138/33 kV transformer, 33 kV switchgear and associated auxiliary systems for the export connection.