Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Installation of the 130 kV subsea export cable for Lillgrund started on 18 December 2006, when the cable-laying vessel NAUTILUS MAXI began laying the cable from the ABB factory loading in Karlskrona along the pre-excavated route in the Öresund between the offshore substation and the Swedish coast.