Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Cable installation for the Lillgrund export system was completed by July 2007, concluding the December 2006–July 2007 construction period for the approximately 7 km three-core 130 kV subsea cable between the offshore substation and shore, alongside the earlier February–April 2007 installation of about 2 km of 130 kV onshore cables linking to E.ON’s Bunkeflo substation.