Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
By mid-November 2021, Red Eléctrica had completed geophysical surveys for the new 132 kV interconnector between the Playa Blanca substation on Lanzarote and the La Oliva substation on Fuerteventura, including bathymetric mapping and seabed characterisation along the 14.5 km submarine route to define the cable corridor and minimise environmental impact.