Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 16 November 2021, Red Eléctrica de España started offshore construction for the new 132 kV electricity interconnection between Lanzarote and Fuerteventura, mobilising the cable‑laying vessel Leonardo Da Vinci to begin laying the 14.5 km submarine cable between the Playa Blanca and La Oliva substations after route surveys and preparation works.