Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Langelands Elforsyning obtained approval from the Danish Energy Agency (Energistyrelsen) for the routing of a new submarine power cable from the wastewater treatment plant at Kragholm to Strynø, comprising 4.7 km of subsea cable and 1 km of onshore cable. This consent for the cable route was a prerequisite for starting the replacement of the defective 40‑year‑old Siø–Strynø cable, after which Langelands Museum was required to inspect the seabed for underwater archaeological remains before installation could begin.