Terna opened the construction site on 20 March to begin laying the 132 kV underground cable interconnection “Sacca Serenella – Cavallino Treporti” in the municipality of Cavallino Treporti. The works, part of the national grid development plan and involving about 14 km of fully buried cable installed via trench excavation or horizontal directional drilling on land and specialised burial equipment offshore, aim to modernise the network supplying the Venice area and enhance the security and reliability of power supply to the Venice Lagoon.