Terna announced that the modernisation of the electricity grid in the Venetian Lagoon, which includes the 132 kV underground cable between the Sacca Serenella and Cavallino primary substations and the related Fusina 2–Sacca Fisola link, involves a total investment of €55 million as part of its 2018–2022 Investment Plan for the Veneto region.