Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
The Italian Ministry for Economic Development granted the necessary consents for Terna’s Venetian Lagoon 132 kV cable project, including the Fusina 2 – Sacca Fisola underground/submarine power line, via Decree EL-106 on 6 August 2009. These development plan consents authorised construction of the new cable links, which were intended to enhance security and reliability of the grid serving Venice and enable the retirement of existing 132 kV overhead lines in the lagoon.