Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Terna began work on the 132 kV underground power line between Fusina 2 and the Sacca Fisola primary substation, the second stretch of its Venetian Lagoon grid modernisation project, which was planned for completion before the end of 2018 to enable dismantling of 6.5 km of existing overhead line in the lagoon.