On 21 February 2019, Terna began decommissioning the existing 132 kV overhead line between Fusina 2 and Sacca Fisola in the Venetian Lagoon, starting demolition works covering 6.5 km of line and 24 pylons, most of them located in the lagoon area. This dismantling is part of the lagoon grid modernisation in which the new underground/submarine Fusina 2–Sacca Fisola cable link replaces the former overhead connection.