Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Cable laying operations for the Kvernesfjorden interconnector between Rokset and Stokkeneset in Møre og Romsdal are scheduled to start on 5 November 2023, with activities planned through 30 November 2023, using the vessels Nautilus Maxi and Nautilus Survey for diving-supported cable installation and Nautilus Balder as a guard vessel along the defined precautionary cable route.